When an intruder reaches a plant through a vendor's remote access account, the decisions that matter most are about safety and production, and they are made by people who rarely rehearse them together. This template is a ready-to-run tabletop exercise in which a compromised integrator account is used to reach the OT network, an engineering workstation and an HMI at a fictional manufacturing plant. It gives a timed inject script, roles, the decisions each inject should force, regulator notification triggers and an after-action template. It is written for OT security leads, plant and operations managers, process safety engineers and incident response coordinators, and it assumes you already have an OT incident response plan to test. The scenario is fictional and describes no real site; it contains no attack instructions. For the response procedure itself, see If your OT remote access and historian is compromised; for running exercises in general, see the Tabletop Exercise Guide.
Key takeaways
- Safety outranks containment. Every inject asks who can order manual operation or a controlled shutdown, on what evidence, and how quickly; if the room cannot answer, that is the main finding.
- Vendor access is the test subject. The scenario checks whether third-party accounts are individually named, time-limited, protected with phishing-resistant MFA, brokered through a DMZ and recorded.
- OT and IT must share one timeline. The script forces the control room, OT engineers, the IT SOC and the integrator to reconcile what each sees.
- Notification clocks start early. Operators of essential services under the UK NIS Regulations must notify their competent authority within 72 hours of becoming aware of a reportable incident; the exercise makes someone own that decision.
- The output is a corrective action list. The after-action template turns observations into owned, dated fixes, not just a discussion record.
How to use this template
- Replace text in square brackets, such as [Organisation], [Plant], [Integrator] and [Line 2], with your own names, systems and contracts. Bracketed numbers are suggestions.
- The script runs in about [3 hours] of real time and covers roughly 72 hours of scenario time in four injects. Each inject has a timed script, the questions for the room and the decisions the facilitator listens for.
- Bring the real artefacts: the OT incident response plan (see the OT Incident Response Plan Template), the remote access register and request forms, the OT asset register, network drawings, the safety case or HAZOP summary for the process in scope, and the integrator contract. Finding them during the session is part of the test.
- Pick a real process line and a real integrator relationship to stand in for the fictional ones, so access and ownership questions are honest. Keep the session discussion-based: nobody touches live systems.
- The structure follows the design, development, conduct and evaluation stages described in NIST SP 800-84 and the package format of the CISA Tabletop Exercise Packages (objectives, scenario, module questions, after action report). NIST SP 800-82 Rev. 3 is the OT security reference for expected actions.
- Use a facilitator from outside the plant chain of command where possible, and run a hot wash immediately after the session while memories are fresh.
Scenario overview and objectives
[Plant] is a continuous process manufacturing site run by [Organisation]. Its control system includes a SCADA server, two HMIs in the control room, an engineering workstation used to change PLC logic, a process historian replicated to an IT-facing DMZ and a safety instrumented system (SIS) that is independent of the basic process control system. [Integrator] supports the PLCs under a service contract and connects through a remote access gateway in the OT DMZ. Over the past year the integrator's technicians have shared one named account "for convenience", and its MFA was moved to a push app on a technician's personal phone.
A threat actor has obtained the account's password from a credential leak and tricked the technician into approving an MFA push. The scenario maps to MITRE ATT&CK for ICS techniques T0822 External Remote Services, T0859 Valid Accounts, T0886 Remote Services, T0840 Network Connection Enumeration and T0836 Modify Parameter, with possible impacts T0832 Manipulation of View and T0813 Denial of Control. The Colonial Pipeline attack is a reminder of how much damage one remote access account can do: an unused VPN account without MFA led to a precautionary pipeline shutdown; see the Colonial Pipeline ransomware attack.
Objectives
- Confirm that [Organisation] can detect and attribute anomalous third-party remote access within [1 hour].
- Confirm that authority to move to manual operation or controlled shutdown is defined, known and exercisable at any hour.
- Test whether vendor remote access can be cut quickly without losing essential support, and whether it can be restored safely.
- Test OT and IT coordination, evidence preservation and the integrator's contractual obligations during an incident.
- Test regulatory, customer and internal communication decisions, including who decides the NIS notification.
Participants and roles
| Role | Who | Exercise responsibility |
|---|---|---|
| Facilitator | [OT security lead or external facilitator] | Delivers injects on time, keeps players to what they know, asks the discussion questions |
| Scribe and timekeeper | [Named person] | Records scenario time, decisions, owners and gaps |
| Plant manager | [Site leader] | Production and shutdown decisions, site incident command |
| Shift supervisor or control room lead | [Operations] | What operators see, manual operation capability, staffing |
| Process safety engineer | [Safety lead] | SIS status, safe states, hazard consequences |
| OT engineer | [Control systems engineer] | PLC logic, engineering workstation, backups and golden images |
| IT SOC and incident manager | [SOC lead] | Identity and gateway logs, IT side containment, evidence |
| Identity and access lead | [IAM or PAM owner] | Third-party accounts, MFA, session recording, credential rotation |
| Integrator liaison | [Vendor manager or the integrator's own representative] | Contract terms, technician accounts, the integrator's own investigation |
| Legal, compliance and communications | [Named people] | Regulator notification, insurer, customers, staff messages |
Inject 1: anomalous remote access
Scenario time: Saturday 02:10 (T+0). The remote access gateway shows a session from [Integrator]'s shared account. No work order exists. The source IP is in a country where the integrator has no staff. The session lasts 40 minutes. On Monday at 07:30 (T+53h in a slow-detection variant, or T+15 minutes in a fast variant) the SOC's identity alert fires for an MFA approval from an unusual location.
- Questions for the room: Who receives gateway alerts out of hours? Can you tell which technician used the account? Is there a session recording? Who can disable the account, and does that also cut a legitimate support session?
- Decisions to listen for: disable or restrict the account; call the integrator through a known contact, not one from the session; preserve gateway, identity and firewall logs; open an incident with a severity level.
- Controls tested: named accounts per technician, approval-based or time-limited access, phishing-resistant MFA, session brokering and recording, and alerting outside business hours. See the OT Remote Access Guide.
Inject 2: HMI and engineering workstation activity
Scenario time: T+3h (or Monday 09:00 in the slow variant). The OT engineer finds an RDP logon to the engineering workstation from the gateway at 02:25, and the PLC programming software shows the project for [Line 2] was opened. No logic download is logged. Operators report that one HMI screen briefly showed a flow value that did not match a local field gauge. The historian copy in the DMZ looks normal.
- Questions for the room: Can you confirm whether PLC logic or setpoints changed? Do you have a known-good logic backup and a way to compare it? Can operators trust the HMI, and what independent readings exist? Is the SIS affected or independent?
- Decisions to listen for: isolate the engineering workstation without powering it off; compare running PLC logic with the golden copy; post operators at local gauges; increase field rounds; involve the integrator's engineers under supervision.
- Controls tested: engineering workstation access control, PLC change logging, golden images (see the OT Backup, Recovery and Golden Image Guide), and OT network monitoring that sees east-west traffic (see the OT Network Security Monitoring Guide).
Inject 3: production and safety decision
Scenario time: T+6h. A logic comparison finds that two alarm thresholds on [Line 2] were changed at 02:31. The process is running within limits but the alarms would now trigger later than designed. The SIS trip settings appear unchanged. A large customer order ships on [Wednesday], and the commercial director asks whether the line can keep running.
- Questions for the room: Who has authority to order manual operation or a controlled shutdown, and is that written down? Can you run [Line 2] manually, with what staff, for how long? What is the safe state, and how long does a controlled shutdown and restart take? Do you trust other lines that the account could reach?
- Decisions to listen for: the process safety engineer's view leads; restore alarm thresholds from the verified backup or move to manual operation; record who decided and why; do not let commercial pressure override the safety case.
- Controls tested: documented shutdown authority, practised manual operation (one of the five primary OT mitigations published by CISA, FBI, EPA and DOE), management of change for emergency logic restores (see OT Management of Change for Cyber), and the cyber-informed HAZOP (see the OT Cyber Physical Risk and Safety Guide).
Inject 4: recovery and communication
Scenario time: T+24h to T+72h. The integrator confirms the technician's credentials were exposed and that the shared account is used at [three] other customer sites. A local journalist asks about "a cyber attack at the plant". Insurers want a notification. Engineering wants the integrator back online to support Monday's restart.
- Questions for the room: Is this a reportable incident under your regulatory regime, who decides and by when? What do you tell staff, customers and the press? On what conditions does remote access return, and who signs it off? What other credentials must be rotated?
- Decisions to listen for: notification decision recorded against the rule and the clock; replace the shared account with named, time-limited accounts before reconnection; rotate engineering workstation, gateway and PLC project passwords; staged reconnection with monitoring; a holding statement approved by legal.
- Controls tested: notification procedure, third-party contract clauses on incident cooperation and access, credential rotation runbooks, and staged reconnection.
Inject summary
| Inject | Scenario time | Trigger | Expected decisions | Owner |
|---|---|---|---|---|
| 1 | T+0 (Sat 02:10) | Unscheduled integrator session, MFA from unusual location | Disable account, call integrator on known contact, preserve logs, declare incident | SOC lead, IAM lead |
| 2 | T+3h | RDP to engineering workstation, PLC project opened, HMI mismatch | Isolate workstation, compare logic, local gauges, check SIS independence | OT engineer, shift supervisor |
| 3 | T+6h | Alarm thresholds changed, commercial pressure | Manual operation or controlled shutdown, restore verified logic under emergency change | Plant manager, process safety engineer |
| 4 | T+24h to T+72h | Integrator confirms exposure, press and insurer enquiries | Notification decision, rotate credentials, conditional staged reconnection, communications | Compliance, communications, vendor manager |
Regulator notification triggers
| Regime | Who it covers | Trigger and clock |
|---|---|---|
| UK NIS Regulations 2018, regulation 11 | Operators of essential services | Notify the designated competent authority in writing without undue delay and no later than 72 hours after becoming aware of an incident with a significant impact on the continuity of the essential service |
| EU NIS2, Article 23 | Essential and important entities in EU member states | Early warning within 24 hours, incident notification within 72 hours and a final report within one month of the incident notification, as transposed nationally |
| US CIRCIA | Covered entities in critical infrastructure | 72 hours for covered incidents and 24 hours for ransom payments once the final rule takes effect; reporting is voluntary until then |
| UK GDPR | Any controller, if personal data is affected | Notify the ICO within 72 hours where a personal data breach is likely to result in a risk to individuals |
Sector regulators may add their own rules, and contracts with customers or insurers often impose shorter clocks. Name the person who decides, record the time of awareness, and note that the UK Cyber Security and Resilience Bill was still before Parliament when this page was checked; see the UK Cyber Security and Resilience Bill Guide.
Discussion questions
- How many third-party accounts can reach OT today, and how many are shared between people?
- Would an out-of-hours session without a work order raise an alert, and who would act on it?
- If the HMI cannot be trusted, what independent view of the process do operators have?
- Who has written authority to move to manual operation or shut down, and has that person practised it?
- Can you prove PLC logic is unchanged, and how long would that take for every line?
- What evidence would you lose by rebooting the engineering workstation or the gateway?
- What does the integrator contract say about notifying you of their own compromise, and about joining your investigation?
- What conditions must be met before remote access is restored, and who signs off?
- Which regulator, if any, would you notify, and when does the clock start?
After-action review
Hold a hot wash straight after the session and a fuller debrief within [two weeks]. Record findings in the format below and track each corrective action to closure; the Tabletop Exercise After Action Report Template gives a full report layout.
| Field | What to record |
|---|---|
| Exercise details | Date, scenario version, participants by role, facilitator, scope (site, lines, systems) |
| Objectives met | For each objective: met, partly met or not met, with the evidence observed |
| Strengths | Decisions and capabilities that worked and should be kept |
| Areas for improvement | Gap, the inject where it showed, impact on safety, production or recovery |
| Corrective actions | Action, owner, due date, framework reference, status |
| Decision log review | Time each key decision was made against the target (account disabled, manual operation, notification) |
| Plan updates | Changes needed to the OT incident response plan, remote access procedure, contracts and contact lists |
| Next exercise | Date, and whether to step up to a functional or simulation exercise |
Track these measures across exercises: time to disable a compromised third-party account; time to confirm PLC logic integrity for one line; percentage of third-party OT accounts that are named and MFA protected; percentage of corrective actions closed by due date; and time to a recorded notification decision.
Framework mapping
| Exercise element | NIST CSF 2.0 | NIST SP 800-53 Rev 5 |
|---|---|---|
| Third-party remote access control | PR.AA-05 | AC-17 Remote Access |
| Coordinated response with the integrator | RS.MA-01 | IR-4 Incident Handling |
| Notification decisions | RS.CO-02 | IR-6 Incident Reporting |
| Recovery and staged reconnection | RC.RP-01 | CP-10 System Recovery and Reconstitution |
| Exercise and lessons learned | ID.IM-02 | IR-3 Incident Response Testing |
Practitioner checklist
- Agree objectives, scope and the stand-in process line with the plant manager and process safety engineer before the session.
- Invite the integrator or a vendor manager who can speak for the contract.
- Collect the remote access register, the OT incident response plan, network drawings and the logic backup procedure in advance.
- Confirm in writing who holds authority to order manual operation and controlled shutdown, day and night.
- Replace shared third-party accounts with named, time-limited accounts protected by phishing-resistant MFA and session recording.
- Test that PLC logic can be compared with a verified golden copy for at least one line.
- Map each notification regime to a named decision owner and the clock that applies.
- Run the hot wash the same day and publish corrective actions with owners and dates within [two weeks].
Standards and references
- NIST: SP 800-82 Rev. 3 Guide to Operational Technology (OT) Security
- NIST: SP 800-84 Guide to Test, Training, and Exercise Programs for IT Plans and Capabilities
- CISA: Tabletop Exercise Packages
- CISA: Primary Mitigations to Reduce Cyber Threats to Operational Technology
- MITRE ATT&CK for ICS: T0822 External Remote Services
- legislation.gov.uk: The Network and Information Systems Regulations 2018, regulation 11
- CISA: Cyber Incident Reporting for Critical Infrastructure Act (CIRCIA)
Related NHI Mgmt Group resources: If your OT remote access and historian is compromised · OT Incident Response Guide · OT Third-Party and Integrator Access Guide · OT and ICS Identity and Access Guide