Many ISO 27001 programmes slip not because the controls are hard, but because nobody owns the plan: tasks start in the wrong order, evidence starts too late, and the Stage 2 date is booked before the ISMS has run. This template gives [Organisation] a fillable project plan for a first certification to ISO/IEC 27001:2022, from charter and scope through to the Stage 2 audit and handover to business as usual. It sets out phases, named owners, milestones, go or no-go gates and a reporting rhythm, with placeholders you replace with your own dates and people. It is written for ISMS managers, programme managers and GRC leads running the project, and for sponsors who need to see whether it is on track. What the standard requires, and the clause-by-clause readiness checks, are covered in the ISO 27001 Certification Guide and the ISO 27001 Certification Readiness Checklist; this page is the schedule that gets you there.
How to use this template
- Replace text in square brackets, such as [Organisation], [Sponsor], [ISMS manager], [Certification body] and [Week n], with your own names and dates.
- Copy sections 3 and 4 into your project tool (spreadsheet, Jira, Planner or similar) as tasks. Keep the task IDs (P1.1, P2.3) so status reports, the RAID log and the gate packs refer to the same items.
- Durations are samples for a single-site organisation of roughly 50 to 500 staff with one main cloud platform. Stretch them for multiple sites, heavy outsourcing or a low starting point; shorten them only where the gap assessment shows existing practice.
- Schedule backwards from nothing. Plan forwards from the gap assessment, then book audit dates once the operating period in phase 5 is in the plan.
- Clause numbers (4.1 to 10.2) and Annex A control numbers (5.1 to 8.34) refer to ISO/IEC 27001:2022, which includes Amendment 1:2024 on climate change. Confirm wording against your licensed copy of the standard.
1. Project charter and scope
Complete this before any other task. The sponsor signs it, and it is the first record of leadership commitment (clause 5.1).
| Field | Entry |
|---|---|
| Objective | [Organisation] achieves accredited certification to ISO/IEC 27001:2022 for [scope] by [target month]. |
| Business driver | [Customer contract requirement / tender requirement / regulator expectation / internal risk reduction] |
| Draft ISMS scope (clause 4.3) | [Products, services, locations, teams and platforms in scope; interfaces and dependencies with what is out of scope] |
| Sponsor | [Name, role]: owns budget, chairs the steering group, signs gates |
| Project lead | [ISMS manager]: owns this plan and the RAID log |
| Target dates | Stage 1: [date]. Stage 2: [date]. Certificate decision: [date]. |
| Budget | Internal effort [person-days], tooling [amount], certification body fees [amount], consultancy if used [amount]. See the ISO 27001 Certification Cost and Timeline Guide. |
| Out of scope for this project | [For example: other ISO standards, second-site expansion, SOC 2 report] |
| Known constraints | [Freeze periods, peak trading, major migrations, key staff leave] |
2. Roles and responsibilities
Name a person, not a team, for every role. R = responsible, A = accountable, C = consulted, I = informed.
| Activity | Sponsor | ISMS manager | Control owners | IT and security engineering | HR, legal, procurement | Internal auditor |
|---|---|---|---|---|---|---|
| Charter, scope, ISMS policy | A | R | C | C | C | I |
| Risk method and risk assessment | A | R | R | C | C | I |
| Statement of Applicability and treatment plan | A | R | C | C | C | I |
| Policies and procedures | I | A | R | R | R | I |
| Technical remediation | I | A | C | R | I | I |
| Awareness and competence (clauses 7.2, 7.3) | I | A | C | C | R | I |
| Supplier security (5.19 to 5.22) | I | A | C | C | R | I |
| Internal audit (9.2) | I | C | C | C | I | A/R |
| Management review (9.3) | A/R | R | C | I | I | C |
| Certification body selection and audit logistics | A | R | I | I | R (procurement) | I |
The internal auditor must not audit their own work. If the ISMS manager wrote the procedures, use another team or an external internal auditor. See the ISMS Internal Audit and Management Review guide.
3. Phase plan and milestones
Sample timeline for a first certification of about nine months. Each phase ends with a milestone that the next phase depends on.
| Phase | Sample weeks | Main outputs | Milestone (gate) | Owner |
|---|---|---|---|---|
| P1 Mobilise | 1 to 3 | Signed charter, steering group, draft scope, document register, project tool set up | M1: charter signed | [Sponsor] |
| P2 Gap assessment and context | 3 to 6 | Gap assessment against clauses 4 to 10 and Annex A, context and interested parties (4.1, 4.2, including the climate change decision), final scope (4.3), asset and identity inventory | M2: scope and gap report approved | [ISMS manager] |
| P3 Risk and SoA | 6 to 12 | Risk method (6.1.2), risk assessment, treatment plan (6.1.3), Statement of Applicability, objectives (6.2), risk owner acceptance | M3: SoA and treatment plan approved | [ISMS manager] |
| P4 Build | 10 to 22 | Policies and procedures, technical remediation, awareness programme, supplier reviews, metrics defined (9.1) | M4: controls in operation | [Control owners] |
| P5 Operate and evidence | 20 to 32 | Records from operating controls: access reviews, changes, incidents, vulnerability scans, training completion, backup restores | M5: operating records for every SoA control | [Control owners] |
| P6 Internal audit and management review | 28 to 33 | Internal audit of all clauses and a sample of controls, nonconformities and corrective actions (10.2), management review with all required inputs | M6: ready for Stage 1 | [Internal auditor], [Sponsor] |
| P7 Stage 1 | 34 | Documentation and readiness review by [Certification body]; areas of concern listed | M7: Stage 1 concerns closed | [ISMS manager] |
| P8 Stage 2 and decision | 38 to 44 | Stage 2 audit, nonconformity corrections submitted, certification decision | M8: certificate issued | [Sponsor] |
| P9 Handover | 44 onwards | Year 2 calendar, surveillance preparation, project closed into business as usual | M9: project closed | [ISMS manager] |
The interval between Stage 1 and Stage 2 is set by your certification body. As one example, Schellman's published process schedules Stage 2 no less than one month and no more than nine months after Stage 1 is completed. Leave room in the plan for that gap rather than booking the two back to back.
4. Workstreams and task list
Copy these tasks into your tool and add owners, start and due dates. Status values: Not started, In progress, Blocked, Done (evidence filed).
| ID | Task | Clause or control | Evidence when done | Owner | Due |
|---|---|---|---|---|---|
| P1.1 | Charter signed and steering group terms agreed | 5.1, 5.3 | Signed charter, terms of reference | [ ] | [ ] |
| P1.2 | Document register with owner, version and review date | 7.5 | Register file | [ ] | [ ] |
| P2.1 | Gap assessment against clauses and Annex A | 4 to 10, Annex A | Gap report with ratings and owners | [ ] | [ ] |
| P2.2 | Context, interested parties and climate change decision recorded | 4.1, 4.2 | Context document | [ ] | [ ] |
| P2.3 | Scope statement with boundaries and interfaces | 4.3 | Approved scope | [ ] | [ ] |
| P2.4 | Asset inventory including non-human identities (service accounts, API keys, workload identities) | 5.9, 5.16 | Inventory export with owners | [ ] | [ ] |
| P3.1 | Risk method: criteria, scales, acceptance threshold | 6.1.2 | Approved method | [ ] | [ ] |
| P3.2 | Risk assessment run and register populated | 6.1.2, 8.2 | Dated risk register | [ ] | [ ] |
| P3.3 | Treatment plan and residual risk acceptance by risk owners | 6.1.3, 8.3 | Signed treatment plan | [ ] | [ ] |
| P3.4 | Statement of Applicability with justification for every control | 6.1.3 d) | Approved SoA | [ ] | [ ] |
| P3.5 | Security objectives with measures and owners | 6.2 | Objectives record | [ ] | [ ] |
| P4.1 | ISMS policy and topic-specific policies approved | 5.2, 5.1 (Annex A) | Approved policies | [ ] | [ ] |
| P4.2 | Remediation backlog from the treatment plan delivered | Per SoA | Closed tickets | [ ] | [ ] |
| P4.3 | Awareness training launched and competence records kept | 7.2, 7.3, 6.3 (Annex A) | Completion report | [ ] | [ ] |
| P4.4 | Supplier inventory and security reviews of critical suppliers | 5.19 to 5.22 | Supplier register, reviews | [ ] | [ ] |
| P4.5 | Monitoring and measurement defined (what, how, when, who) | 9.1 | Metrics plan | [ ] | [ ] |
| P5.1 | Access review completed for human and non-human accounts | 5.18, 8.2 | Signed review, revocation tickets | [ ] | [ ] |
| P5.2 | Incident, change, vulnerability and backup records collected | 5.24 to 5.27, 8.8, 8.13, 8.32 | Populations with timestamps | [ ] | [ ] |
| P6.1 | Internal audit programme and audit executed | 9.2 | Audit plan and report | [ ] | [ ] |
| P6.2 | Corrective actions raised and tracked | 10.2 | Corrective action log | [ ] | [ ] |
| P6.3 | Management review held with all required inputs | 9.3 | Minutes and decisions | [ ] | [ ] |
| P7.1 | Certification body contracted and audit dates confirmed | Audit logistics | Signed contract, audit plan | [ ] | [ ] |
| P8.1 | Stage 2 findings corrected and evidence submitted | 10.2 | Correction evidence pack | [ ] | [ ] |
For the full list of required documents and records behind these tasks, see the ISO 27001 Mandatory Documents and Records Guide. For P3.4 use the ISO 27001 Statement of Applicability Template, and for P3.2 the Risk Register Template.
5. Gate criteria
The steering group holds a short gate review at M2, M3, M6 and M7. A gate passes only when every criterion is met or has a dated, owned exception signed by [Sponsor].
| Gate | Go criteria | If not met |
|---|---|---|
| M2 Scope and gap | Scope approved by [Sponsor]; gap report rated and owned; inventory covers every in-scope platform | Hold P3; a scope that keeps changing invalidates the risk assessment |
| M3 SoA | Every Annex A control marked applicable or excluded with a reason; treatment plan has owners and dates; residual risks accepted | Hold the build of excluded or unowned areas; do not write policies for controls not yet decided |
| M6 Stage 1 ready | Internal audit complete across all clauses; management review held; no open major internal findings; operating records exist for each applicable control | Move Stage 1; the cost of rebooking is lower than a failed Stage 2 |
| M7 Stage 2 ready | Stage 1 concerns closed with evidence; records continue to accumulate; interviewees briefed | Ask [Certification body] to move Stage 2 within its permitted interval |
6. Reporting and RAID log
- Weekly: [ISMS manager] updates task status and the RAID log (risks, assumptions, issues, dependencies) and sends a one-page status to workstream leads.
- Monthly: steering group reviews milestone status (on track, at risk, late), budget burn, top five risks and decisions needed.
- RAID entry fields: ID, type, description, owner, date raised, impact on milestone, action, due date, status.
- Typical RAID entries to seed: control owners unavailable during [peak period]; dependency on a platform migration finishing by [date]; assumption that the identity provider export includes service accounts; risk that a key supplier will not share its own assurance report in time.
7. Resources and budget tracking
| Line | Planned | Actual to date | Forecast | Notes |
|---|---|---|---|---|
| ISMS manager effort | [days] | [ ] | [ ] | [ ] |
| Control owner effort | [days] | [ ] | [ ] | [ ] |
| Engineering remediation | [days] | [ ] | [ ] | [ ] |
| Tooling and licences | [amount] | [ ] | [ ] | [ ] |
| Internal audit (if external) | [amount] | [ ] | [ ] | [ ] |
| Certification body fees (Stage 1, Stage 2) | [amount] | [ ] | [ ] | [ ] |
| Contingency | [10 to 20 per cent] | [ ] | [ ] | [ ] |
8. Handover to business as usual
- Every SoA control has a named owner in a role description, not a project task.
- Recurring activities are in a year 2 calendar: risk assessment review, access reviews, internal audit, management review, supplier reviews, policy reviews and surveillance audit preparation.
- Open corrective actions move from the project tool to the ISMS corrective action log (10.2) with owners and dates.
- Metrics from P4.5 are reported to management at the agreed frequency.
- The project is formally closed by [Sponsor] with a lessons learned note filed as continual improvement input (10.1).
Surveillance starts quickly. In Schellman's published process the first surveillance audit takes place no more than 12 months from the certification decision, and the certificate runs for three years before recertification. See the ISO 27001 Surveillance Audit Checklist.
Implementation guidance
Choosing a delivery model. The right model depends on internal capacity, not organisation size alone.
| Model | Suits | Trade-off |
|---|---|---|
| In-house ISMS manager leads | Organisations with an existing GRC or security function | Slower start; knowledge stays in the organisation |
| Consultant writes, staff operate | Small teams with a hard deadline | Faster documents, but documents the staff did not write are often not followed; auditors test operation, not paperwork |
| Consultant coaches, staff write | Most first certifications | Balanced cost and ownership; needs protected staff time |
| Extend an existing programme (SOC 2, NIST CSF) | Organisations already reporting against another framework | Reuses evidence; map controls first to avoid gaps the other framework does not test |
Where plans usually slip:
- Scope changes after the risk assessment: adding a product or site in phase 4 sends you back to P2.3 and P3.2. Freeze scope at M2 and log any change through the steering group.
- No operating period: the ISMS needs time to generate records. Certification bodies test whether controls operate, and some activities, such as quarterly access reviews, need elapsed time that consultants cannot compress.
- Internal audit squeezed: a rushed audit of a sample of clauses leaves gaps the certification body will find. Plan the full programme in P6 and protect it.
- Non-human identities missed: service accounts, API keys and automation credentials are left out of inventory and access reviews, then appear in Stage 2 sampling. Include them from P2.4. See the Service Account Security Guide.
- Audit booked before the gap assessment: a fixed date set without data forces the project to cut the operating period. Book dates after M3.
Small versus large organisations. A small, single-platform organisation can often combine P1 and P2 and run P4 and P5 together, provided records start as soon as each control goes live. A large or multi-site organisation should run workstreams in parallel with a lead per workstream, and consider a narrower first scope that is extended at surveillance or recertification. Audit time grows with factors such as headcount in scope, number of sites and ISMS complexity, as described in ISO/IEC 27006-1.
Metrics to track the project: milestones on time versus late; tasks overdue by more than two weeks; percentage of applicable SoA controls with an operating record; open gap report items by owner and age; internal audit findings closed on time; and budget burn against forecast.
References: ISO: ISO/IEC 27001 Information security management systems · ISO: ISO/IEC 27002:2022 Information security controls · ISO: ISO/IEC 27005:2022 Guidance on managing information security risks · ISO and IAF: Joint Communiqué on climate change amendments · UKAS: Transition arrangements for ISO/IEC 27001:2022 · Schellman: ISO Certification Services Processes · Schellman: Factors that can affect your ISO 27001 timeline
This template is provided for guidance and must be adapted to your organisation; it does not replace the judgement of your certification body. Related NHI Mgmt Group resources: ISO 27001 Certification Guide · ISO 27001 Certification Readiness Checklist · Gap Assessment vs Readiness Assessment vs Audit · ISMS Internal Audit and Management Review · Information Security Policy Template