NERC CIP-010 is the standard that makes a utility prove it knows exactly what is installed on its high and medium impact BES Cyber Systems, that every change was authorised and checked, and that laptops and USB drives brought to those systems are controlled. It has four requirements: configuration change management (R1), configuration monitoring (R2), vulnerability assessments (R3) and Transient Cyber Assets and Removable Media (R4). This guide goes part by part through what each requirement asks, the clocks it sets, the baseline elements, the transient asset plan sections and the evidence auditors test. For the wider family of standards, start with the NERC CIP Guide.

Status checked 27 November 2026: CIP-010-4 is the enforceable version in the United States; FERC staff record its effective date as 1 October 2022. FERC Order No. 919 (rule effective 26 May 2026) approved CIP-010-5 as part of the virtualisation package; it becomes enforceable under NERC's implementation plan, described below.

Key takeaways

  • The baseline has five fixed elements. Part 1.1 requires operating system or firmware, intentionally installed commercial or open-source software, custom software, logical network accessible ports and applied security patches, each recorded per asset or per group.
  • Every deviation has a 30-day clock. Changes that deviate from the baseline must be authorised and documented, and the baseline updated within 30 calendar days of completing the change.
  • High impact systems carry extra testing and monitoring. Part 1.5 testing before production, Part 2.1 monitoring at least every 35 calendar days and Part 3.2 active assessments at least every 36 calendar months apply to high impact systems.
  • Vulnerability findings need dated action plans. Part 3.4 requires documented results and a remediation or mitigation plan with planned completion dates and status, which FERC auditors have found missing for end-of-life assets.
  • Third-party laptops need verification, not attestation. R4 requires a documented plan for Transient Cyber Assets and Removable Media, and FERC audit staff recommend validating how a vendor's controls are actually implemented on the asset.

Scope

CIP-010-4 applies to Balancing Authorities, Generator Operators, Generator Owners, Reliability Coordinators, Transmission Operators, Transmission Owners and, for specific protection and restoration systems, Distribution Providers (qualifying UFLS or UVLS systems, Remedial Action Schemes, Protection Systems and Cranking Paths). Exemptions cover Cyber Assets at facilities regulated by the Canadian Nuclear Safety Commission, Cyber Assets in communication networks and data links between discrete Electronic Security Perimeters, systems regulated under 10 C.F.R. 73.54, and entities with no high or medium impact BES Cyber Systems. Categorisation under CIP-002 decides which parts apply, so start with the NERC CIP-002 BES Cyber System Categorisation Guide.

Each part names its own Applicable Systems, typically high and medium impact BES Cyber Systems with associated Electronic Access Control or Monitoring Systems (EACMS), Physical Access Control Systems (PACS) and Protected Cyber Assets (PCA).

PartObligationApplicable systems (CIP-010-4)Clock
1.1Develop a baseline configurationHigh and medium impact, with EACMS, PACS, PCAMaintained continuously
1.2Authorise and document changes that deviate from the baselineHigh and medium impact, with EACMS, PACS, PCABefore the change
1.3Update the baseline after a deviating changeHigh and medium impact, with EACMS, PACS, PCAWithin 30 calendar days of completing the change
1.4Determine affected CIP-005 and CIP-007 controls, verify after the change, document resultsHigh and medium impact, with EACMS, PACS, PCABefore and after each deviating change
1.5Test the change before production, where technically feasibleHigh impact onlyBefore implementation
1.6Verify software source identity and integrityHigh and medium impact, with EACMS, PACS, PCABefore a baseline change to OS, firmware, software or patches
2.1Monitor for changes to the baseline, investigate unauthorised changesHigh impact, with EACMS and PCAAt least once every 35 calendar days
3.1Paper or active vulnerability assessmentHigh and medium impact, with EACMS, PACS, PCAAt least once every 15 calendar months
3.2Active vulnerability assessment, where technically feasibleHigh impact onlyAt least once every 36 calendar months
3.3Active assessment before a new asset enters productionHigh impact, with EACMS and PCABefore production use
3.4Document results and a remediation or mitigation action planHigh and medium impact, with EACMS, PACS, PCAWith each assessment
R4Plan for Transient Cyber Assets and Removable Media (Attachment 1)High and medium impact, with PCAContinuous, except CIP Exceptional Circumstances

What changes with CIP-010-5

FERC Order No. 919 approved eleven modified CIP standards, including CIP-010-5, with the rule effective 26 May 2026. NERC's implementation plan sets the effective date as the later of 1 April 2026 or the first day of the first calendar quarter 24 months after the approving order takes effect. Our reading is 1 July 2028, but the order states no fixed date, so confirm it with your Regional Entity; early adoption at six, 12 or 18 months is possible on notice. NERC described the revisions as broadening change management beyond a baseline-only configuration to suit virtualised systems. In the April 2024 Project 2016-02 redline, Shared Cyber Infrastructure (SCI) supporting an Applicable System is added to several parts, Part 1.4 is framed around changes that alter the behaviour of CIP-005 and CIP-007 controls, and Part 2.1 monitoring is reframed around changes to listed security controls, still at least every 35 calendar days. Until enforcement, CIP-010-4 is the version you are audited against.

R1 Configuration change management

R1 asks for documented processes that collectively include Parts 1.1 to 1.6. The baseline in Part 1.1 is the reference every other part depends on.

Baseline elements

PartElementPractical detail to record
1.1.1Operating system or firmware where no independent OS existsProduct, version and build, including firmware on relays, RTUs, switches and firewalls
1.1.2Commercially available or open-source application software intentionally installedName and version; agents for backup, monitoring and anti-malware count
1.1.3Custom software installedInternally developed tools, scripts packaged as software, vendor-customised builds
1.1.4Any logical network accessible portsListening TCP and UDP ports, ideally reconciled with the CIP-007 R1 ports and services justification
1.1.5Any security patches appliedPatch identifier and install date, aligned with the CIP-007 R2 patch evaluation records

Group baselines are allowed, but only hold if every member matches. Keep baselines in a system that supports automated comparison.

Authorising, verifying and testing changes

  • Part 1.2 authorise and document: every change that deviates from the baseline needs a recorded authorisation. Tie it to your change management ticket so the approver, date and scope are traceable.
  • Part 1.3 update within 30 calendar days: the clock starts when the change is completed, not when the ticket closes. Emergency changes made under CIP Exceptional Circumstances still need the baseline updated.
  • Part 1.4 security impact: before the change, determine which required cyber security controls in CIP-005 and CIP-007 could be affected; after it, verify they were not adversely affected and document the results.
  • Part 1.5 test first (high impact): where technically feasible, test the change in a test environment, or in production in a way that minimises adverse effects, that models the baseline. Document the results and the differences between test and production and how they were accounted for.
  • Part 1.6 verify the software: before a change to items 1.1.1, 1.1.2 or 1.1.5, verify the identity of the software source and the integrity of the software, where the source provides a method (for example a published hash or a digital signature). This part came from the supply chain work and does not require renegotiating existing contracts. See the NERC CIP-013 guide for the procurement side and the Code Signing Security Guide for signature checks.

R2 Configuration monitoring

Part 2.1 applies to high impact BES Cyber Systems and their associated EACMS and PCA. The entity must monitor at least once every 35 calendar days for changes to the baseline described in Part 1.1, and document and investigate any unauthorised changes it detects.

  • Automate the comparison: configuration management or file integrity tools that collect installed software, patches and listening ports and compare them with the approved baseline make the 35-day cycle routine. Assets that cannot run agents need scheduled manual collection or passive network data.
  • Close the loop with change records: each detected difference should match a Part 1.2 authorisation; anything else is investigated and documented.
  • Watch the window: schedule the job weekly or fortnightly so one missed run does not breach 35 days.

The Configuration Drift and Baseline Enforcement Guide covers tooling approaches.

R3 Vulnerability assessments

R3 sets three kinds of assessment and a documentation duty.

  • Part 3.1: a paper or active vulnerability assessment at least once every 15 calendar months for high and medium impact systems and their associated EACMS, PACS and PCA.
  • Part 3.2 (high impact): where technically feasible, an active vulnerability assessment at least once every 36 calendar months, in a test environment or in production in a way that minimises adverse effects and models the baseline, documenting differences between test and production.
  • Part 3.3 (high impact, with EACMS and PCA): an active vulnerability assessment before adding a new applicable Cyber Asset to production, except for CIP Exceptional Circumstances and like replacements of the same type of Cyber Asset with a baseline that models an existing baseline.
  • Part 3.4: document the results of the assessments and an action plan to remediate or mitigate the vulnerabilities identified, including the planned date of completion and the execution status of any remediation or mitigation.

The standard does not list what an assessment must contain, but FERC's 2022 CIP audit lessons strongly encouraged including network discovery, network port and service identification, vulnerability review or scanning, and wireless review, and considering radio frequencies beyond Wi-Fi. The same report flagged end-of-life assets without dated action plans. Active scanning of fragile control equipment is best done in a test environment or with vendor guidance. See the ICS Advisory Triage and OT Vulnerability Management Guide for triage once findings exist.

R4 Transient cyber assets and removable media

R4 requires each Responsible Entity with high or medium impact BES Cyber Systems or associated PCA to implement one or more documented plans for Transient Cyber Assets (TCAs) and Removable Media that include the sections in Attachment 1, except during CIP Exceptional Circumstances. Typical TCAs are engineering laptops, protocol analysers and vendor maintenance devices connected for 30 consecutive calendar days or less; Removable Media are USB drives, external disks and similar media.

Attachment 1 sectionRequired elementMethods the standard lists (one or more)
1.1 Entity-managed TCA: managementManage TCAs individually or by group, in an ongoing manner, on demand before connection, or bothDefined in the plan
1.2 Entity-managed TCA: authorisationAuthorise users, locations and uses, limited to what is necessary for business functionsIndividual or group authorisation
1.3 Entity-managed TCA: software vulnerabilitiesMitigate software vulnerabilitiesSecurity patching, live operating system and software executable only from read-only media, system hardening, other methods
1.4 Entity-managed TCA: malicious codeMitigate the introduction of malicious codeAntivirus with managed signature updates, application whitelisting, other methods
1.5 Entity-managed TCA: unauthorised useMitigate the risk of unauthorised useRestrict physical access, full-disk encryption with authentication, multi-factor authentication, other methods
2.1 Third-party TCA: software vulnerabilitiesReview how the other party mitigates vulnerabilitiesReview installed patches, the party's patching process, or other mitigation
2.2 Third-party TCA: malicious codeReview how the other party mitigates malicious codeReview antivirus update level or process, whitelisting, read-only live OS, hardening
2.3 Third-party TCA: decisionDetermine whether additional mitigation is needed and apply it before connectionEntity judgement, documented
3.1 Removable Media: authorisationAuthorise media, users and locations, individually or by groupAuthorisation records
3.2 Removable Media: malicious codeDetect malicious code using a Cyber Asset other than a BES Cyber System or PCA, and mitigate it before connectionDedicated scanning station (kiosk) with logs

Making the plan work in practice

  • Keep a TCA register: each entity-managed laptop or tool, its owner, authorised users, locations, uses, and patch and anti-malware state.
  • Scan every medium, every time: a dedicated scanning kiosk outside the BES Cyber System, with logs of each scan and result, is the most auditable way to meet Section 3.2. Removable media is a proven route into control networks; see MITRE ATT&CK for ICS T0847 Replication Through Removable Media.
  • Verify vendor devices: FERC audit staff found entities accepting vendor attestations without validating how controls were implemented, and recommended validating the specific implementation on the asset, negotiating a right to audit and reviewing external assessments such as SOC 2 reports or ISO 27001 certifications.
  • Control the accounts on TCAs: engineering laptops often hold stored credentials for relays and controllers. Treat those as shared credentials, protect them under Section 1.5, and align with the CIP-007 R5 account controls.

Evidence and common findings

Evidence must be retained for three calendar years, or longer if the entity is found non-compliant, until mitigation is complete and approved. Attachment 2 of the standard gives examples of acceptable evidence for each R4 section.

RequirementEvidence auditors usually ask forAutomation that helps
R1.1 to 1.3Baselines per asset or group; change tickets with authorisation; baseline update dates within 30 days of change completionConfiguration management database linked to the change system
R1.4 and 1.5Pre-change control impact analysis, post-change verification, test records and test versus production differencesChange templates with mandatory CIP-005 and CIP-007 impact fields
R1.6Hash or signature verification records for each installed OS, firmware, software and patchSoftware repository that records verification before release
R2.1Monitoring output at intervals of 35 days or less; investigation records for unauthorised changesScheduled baseline comparison reports
R3Assessment reports, methodology, dated action plans with status, pre-production assessments for new high impact assetsVulnerability tracking linked to the asset inventory
R4TCA and media plan; authorisation records; patch and anti-malware records; third-party review records; kiosk scan logsKiosk logging and TCA check-out records

Metrics

  • Percentage of deviating changes with the baseline updated within 30 calendar days (target 100%).
  • Maximum interval between baseline monitoring runs for high impact assets (target well under 35 days).
  • Unauthorised changes detected per cycle and median time to investigate.
  • Open vulnerability action plan items past their planned completion date.
  • Removable media connections with a matching kiosk scan record (target 100%).

Framework mapping

CIP-010 requirementNIST SP 800-53 Rev. 5NIST CSF 2.0
R1.1 baselineCM-2 Baseline ConfigurationPR.PS-01
R1.2 to 1.5 change control and testingCM-3 Configuration Change Control, CM-4 Impact AnalysesPR.PS-01
R1.6 software integrityCM-14 Signed ComponentsPR.PS-01
R2 configuration monitoringCM-3 Configuration Change ControlDE.CM-09
R3 vulnerability assessmentsRA-5 Vulnerability Monitoring and ScanningID.RA-01
R4 transient assets and mediaMP-7 Media Use, SI-3 Malicious Code ProtectionDE.CM-09

In ISO/IEC 27001:2022 Annex A, the closest controls are 8.9 Configuration management, 8.32 Change management, 8.8 Management of technical vulnerabilities and 7.10 Storage media.

Common findings

  • Baselines that do not match reality: a group baseline claims identical builds, but sampled devices have extra software or different firmware.
  • Late baseline updates: the change is made during an outage and the baseline is updated when the ticket is closed weeks later, past 30 days.
  • Part 1.4 done on paper only: the impact field says "none" by default and no post-change verification of ports, logging or access controls is recorded.
  • Action plans without dates: end-of-life or unpatchable assets are listed as accepted risk with no planned completion date or status, contrary to Part 3.4.
  • Vendor laptops on trust: a vendor's signed attestation is accepted without checking patch and anti-malware state on the actual device.

Practitioner checklist

  • Record all five Part 1.1 baseline elements per asset or defined group, in a system that supports automated comparison.
  • Link every deviating change to an authorisation, a CIP-005 and CIP-007 impact analysis and post-change verification.
  • Verify software source identity and integrity before installing OS, firmware, software or patches, and keep the record.
  • Run high impact baseline monitoring at least fortnightly so the 35-day limit is never at risk.
  • Schedule 15-month assessments per asset group and 36-month active assessments for high impact systems, with dated action plans.
  • Operate a logged scanning kiosk for all Removable Media and a register of entity-managed TCAs.
  • Check third-party TCAs on the device before connection and record the Section 2 review.
  • Plan the move to CIP-010-5, including Shared Cyber Infrastructure, against the date confirmed with your Regional Entity.

Standards and references

This guide summarises NERC CIP-010 and is not legal advice. Confirm obligations and effective dates with the standard text and your Regional Entity. Related NHI Mgmt Group resources: NERC CIP Guide · NERC CIP-004 Guide: Personnel Risk Assessment, Training and Access Revocation · NERC CIP-015 Internal Network Security Monitoring Guide · Change Management Security

PDF for subscribers

Take this guide with you

Every section, table and checklist in one PDF, with links to the sources and related guides. Subscribe to our weekly NHI & AI Identity Journal and we’ll email you a download link.

Free weekly newsletter

Subscribe to the NHI & AI Identity Journal

The latest on NHI and Agentic AI security – articles, research, breaches, news and events every week.

Bonus 33% off our NHI Course when you subscribe.

PDF Downloads for Newsletter Subscribers

Get the guide

Enter your details and we’ll email you a download link.

The full guide is free to read online. The PDF is a thank you for subscribing.

Fill in all fields marked * and tick both boxes to continue.